What Commercial Door Installation Pros Do — A GC’s Field Guide

General contractors juggle dozens of trades, but Division 8 (segment of construction) often looks deceptively simple—“hang a door, slap on the hardware.”

In reality, door specialists orchestrate airtight tolerances, life-safety code, and sequencing that can make or break close-out.

1️⃣ Pre-Install Reality Check

  • Rough-opening verification—plumb, level, square, and within ¹⁄₁₆ in. per SDI standard.

  • Frame anchorage review—masonry, stud, or welded: each demands the right anchor pattern and fire-rating labels before walls close.

  • Hardware staging—hinges, closers, electrified locks, and connection points are pre-kitted and cross-checked against the approved submittal to prevent costly punch-lists.

2️⃣ Installation & QC

  • Frame set “PLS” (plumb-level-square) with diagonal bracing until grout cures.

  • Door leaf clearances verified: ⅛ in. head/jamb, ¹⁄₁₆ in. meeting-edge for pairs—per ANSI/SDI 100.

  • Hardware templated, torqued to spec, and fire-rated assemblies inspected under NFPA 80.

3️⃣ Turnover Best Practices

  • Functional testing (swing, latch, closer sweep) witnessed by the GC and recorded in the close-out package.

  • O&M documentation—including hinge lubrication schedule and annual fire-door inspection checklist.

Take-away: Engage your door subcontractor early, lock submittals before rough framing, and budget a joint pre-installation meeting. You’ll shave days off punch-list and keep Certificate-of-Occupancy on track.

ANSI - American National Standards Institue

SDI - Steel Door Institute

NFPA - National Fire Protection Association

Previous
Previous

Bay Area Construction Pulse: June 2025

Next
Next

Subcontractor Synergy: Why the GC Is Our Command Center